ComEd Transmission L8221- Noble-Kinzie to Goose Island Terminal
Sicon Engineering was responsible for the design of approximately 3200 linear feet of 9-6” PVC conduit package from Noble-Kinzie Terminal to Goose Island Terminal, including the installation of two new transmission manholes, one transmission manhole expansion, and one manhole roof replacement. Sicon developed a 3D model of existing utilities along the project route from utility atlas information, field measured utility invert information, and manhole scans in order to perform the civil underground design.
Sicon was responsible for test hole plans, restoration plans, traffic control plans, and cable pulling calculations. Sicon designed earth retention systems for trench shoring including deep excavation trenches, manhole shaft shoring, box tunnel shoring, reinforced duct package for railroad crossing, and several utility supports. To secure permits, Sicon worked with the Chicago Department of Transportation. In addition to design phase activities, Sicon provided construction support and record survey to develop as-built drawings upon completion of construction. As-built drawings were developed in CAD and brought into GIS to update ComEd’s database.
Sicon’s Feeder Line 6 project is a high pressure natural gas pipe replacement job that runs from approximately 3300 South in Salt Lake City to the top of Draper’s Corner Sicon between Salt Lake and Utah Counties. The nearly 95,288 foot length of 12” high pressure steel pipe runs through a variety of state and neighborhood roads as well as traversing a few Sicons. Sicon is providing the full range of construction services: project engineering, milling, traffic control, excavation, welding, pipe installation, trench backfill, asphalt and concrete paving, landscape and forested area restoration, coordination with the public and municipalities, etc.
Feeder Line Replacement – U.S. 89, Utah
On this project, Sicon replaced approximately 18 miles of high pressure feeder
line with new 12-inch-diameter steel pipe along U.S. 89 from Alpine to Provo.
Since U.S. 89 is one of Utah County’s few continuous north-south routes, the
project had potential to cause significant traffic delays. Coordination with
Utah Department of Transportation was critical to identifying the installation
methods and traffic control measures to keep traffic moving.
Most construction that required lane closures was done at night. Lanes then
re-opened during the day. Movable barriers were used in some work zones to allow
opening lanes during peak travel times. In other areas, directional boring was
used to eliminate the need to dig open trenches, which helped minimize the
impact to traffic on heavily travelled stretches. These installation methods, in
addition to the careful determination of hours of operation based on traffic
analysis, resulted in very few complaints from local businesses and residents.
The project was also a top three finalist for UDOT’s Keeping Utah Moving Award
in the Team category.